Conduct both a forward and backward pass using AON notation.
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
- Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
- Identify all paths through the network. Which is the critical path?
- Which activities have slack time?
- Identify all burst activities and merge activities.
- Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
- ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
- Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
- Identify all paths through the network. Which is the critical path?
- Which activities have slack time?
- Identify all burst activities and merge activities.
- Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
- ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
- Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
- ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
- Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
- Identify all paths through the network. Which is the critical path?
- Which activities have slack time?
- Identify all burst activities and merge activities.
- Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
- Identify all paths through the network. Which is the critical path?
- Which activities have slack time?
- Identify all burst activities and merge activities.
Leave a Reply
Want to join the discussion?Feel free to contribute!